Featured Project

Wyecroft Road & Dorval Drive Remediation

Location
Oakville, ON

Milestone Environmental Contracting Inc. Wyecroft Road & Dorval Drive Remediation project for soil remediation at two properties in Ontario.

Type of Work
  • Soil and Groundwater Remediation
Key Services
  • Excavation and Disposal
  • Shoring
Key Highlights
Wyecroft Road
  • Design and installation of a pile and lagging shoring system to facilitate excavation of the impacted soil.
  • Excavation and off-site disposal of 9,540 metric tonnes of non-hazardous contaminated soil to a licensed facility.
  • Supply, placement, grading and compaction of over 8,060 metric tonnes of imported select subgrade backfill material.
Dorval Drive
  • Design and installation of a concrete underpinning system to protect a high-voltage buried concrete encased hydro duct.
  • Design and installation of a caisson wall shoring system to facilitate the excavation of impacted soils.
  • Excavation and off-site disposal of 2,695 metric tonnes of non-hazardous contaminated soil to a licensed facility.
  • Supply, placement, grading and compaction of over 2,200 metric tonnes of imported select subgrade backfill material.