Featured Project

Location
Hamilton, ON

Major Milestone – Randle Reef Remediation Stage 2 Completion 
Read More »

The Randle Reef Sediment Remediation Project Stage 2 was to dredge 400,000 m3 of contaminated sediments and place them in an Engineered Containment Facility (ECF), treat and dewater the ECF contaminated water prior to placement of fill materials, and isolation capping and thin layer capping of remaining contaminated sediment over some of the work area.

Milestone is completing this project within a Joint Venture with FRPD. Located in the southwest corner of Hamilton Harbour, in the Port of Hamilton, the Randle Reef site is roughly 60 hectares in size.

The site contains approximately 695,000 cubic metres of sediment contaminated with polycyclic aromatic hydrocarbons (PAH) and other toxic chemicals – the largest PAH-contaminated sediment site on the Canadian Great Lakes. The dredging of the contaminated sediment is being completed using a cutter suction dredge that removes material from the lakebed and transports it as a slurry through a pipeline to the ECF. As the slurry containing contaminated sediments is pumped into the ECF, the solids are allowed to settle out, and then the water is pumped mechanically to an upland water treatment plant where it is treated, tested, and discharged back into the harbour. The water treatment system involves removal of total suspended solids and treatment of PAH and metals impacted water.

Type of Work
  • Soil and Groundwater Remediation
  • Heavy Civil Construction
Key Services
  • Dredge and Dewatering
  • Water Treatment
Key Highlights
  • Hydraulic suction dredging and placement of contaminated sediments within the ECF.
  • Second pass dredging.
  • Mechanical debris removal.
  • Design, construct and operate water treatment plant to dewater ECF.
  • Metal works and welding for the pump platform and overflow structure on the ECF.
  • Construction and installation of the underliner drainage pipe and risers in the ECF.
  • Rock backfilling of the ECF between the anchor wall and face wall.
  • Isolation capping of stelco channel.
  • Thin layer capping and thin layer backfilling.
  • Maintenance of staging pad.
  • Turbidity and sheen mitigation and control.
  • Implementation and management of environment, health and safety controls.

For more information about Randle Reef click here.

 

Want to know more about this project?

Signup to our Newsletter!

Keep up to date with Milestone Environmental, by subscribing to our periodic newsletter!