Milestone Environmental Contracting Inc. was awarded a contract by the Yukon Government for environmental restoration services to remediate hydrocarbon impacted soils using thermal desorption at the Marwell Tar Pit in Whitehorse.
Key Challenges
Working through northern climate.
Management of activities with limited space considerations.
Key Solutions
All treatment completed onsite using enhanced thermal conduction units.
Project Scope
Site setup including clearing, stripping and grubbing.
Extreme site regrading for treatment pad commissioning.
Mobilization, installation, operation, and decommissioning of water treatment system.
Excavating 52,00 tonnes of material.
Treatment of 32,000 tonnes of hydrocarbon impacted material using thermal desorption process.
Site restoration including regrading, placement of topsoil and reseeding.