Featured Projects  >  North Apron Remediation

North Apron Remediation

Type of Work

Soil and Groundwater Remediation

Key Services

Excavation and Disposal

Location

Whitehorse, YT

Year

2017

Project Scope

  • Establishment of site security and control zones, installation of aviation low profile barriers and working within Airside Vehicle Operator’s Permits (AVOPs) requirements.
  • Material transportation to overburden stockpile or on site LTF.
  • Off site disposal (as required) of PHC impacted soil.
  • Supply and placement of imported drain rock and 80mm minus backfill.

Key Highlights

  • Project executed during extreme winter conditions. Frost ripping required to commence excavation.
  • Ensured there were no interruptions to the ongoing maintenance equipment, access to fueling facilities and no disruption to the airport operations.
  • Continued maintenance to ensure snow was cleared and ice conditions on roads were mitigated using specialized sand for airport operations.